Regional Council completes rapid stopbank breach repairs on Ngaruroro and Tutaekuri rivers

Jon Kingsford image

Rapid repairs of around five kilometres of stopbank breaches on the Ngaruroro and Tutaekuri rivers have been completed by the Hawke’s Bay Regional Council.

Council Chair Hinewai Ormsby says this is a significant milestone, three months on from Cyclone Gabrielle.

“These repairs were an absolute focus for the Regional Council, and have been completed in a short time frame, thanks to the hard work of a dedicated team of contractors and consultants, all of whom were motivated to get it done, to protect our community.”

Cyclone Gabrielle brought unprecedented flooding which caused around 5.6 kms of breaches in the 248km stopbank network, and further parts of the network were damaged by erosion.

Regional Council’s Jon Kingsford who has led the Rapid Repair Team says they took gravel from areas near breach sites to build the core of the stopbank, and then put in place a silt or clay cap, a topsoil layer and then a grass layer on top.

“The grass is important to make sure those layers bind together and resist any flow of river across that surface,” he says.

There are crews working by Central Hawke’s Bay rivers finishing the repair of stopbank breaches.

Now the crews are nearing the completion of all breach sites, they will move on to repair scour and erosion sites and this will take up to three months.

“While the hard work to close the big holes in the stopbanks is done, we still have work ahead to ensure that our stopbanks are back to pre-cyclone standard.”

“I do want to thank the fantastic support we have received from our local contractors and consultants, and those who came to work with us from outside the region. We couldn’t have done this without them.”

Chair Ormsby says the Regional Council review of the flood scheme will look at the ways it might be improved so the scheme can behave in a known way during large flooding events, and this may include changes such as secondary flow paths or catchment detention.

“We will do this in collaboration with our community and will gather feedback from people who were impacted by the cyclone,” she says.

Check out our video of Jon talking about the repairs: https://youtu.be/X7zjTXkDHys

For more information,  and to see map of repairs, go to hbrc.govt.nz and search #progress

 

8 June 2023

Back to News & Media

Disclaimers and Copyright
While every endeavour has been taken by the Hawke's Bay Regional Council to ensure that the information on this website is accurate and up to date, Hawke's Bay Regional Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hawke's Bay Regional Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hawke's Bay Regional Council - www.hbrc.govt.nz / +64 6 835 9200 / info@hbrc.govt.nz