skip to main content

Ōhiti Road | Ōmāhu

We’re building 2.1 km of stopbanks on both sides of the Ohiwia stream and raising roads to meet the stopbanks– along with stream works, drainage upgrades, and erosion protection. The start of construction has seen 11 Ōhiti Road properties meet the requirements to move to Category 1.

About this project

Part of the Government’s North Island Weather Event (NIWE) recovery programme, the Ōhiti Rd | Omāhu project aims to reduce flood risk for 11 Category 2C properties along Ōhiti Road and nearby. The goal is to reclassify these homes to Category 1 – the lowest risk.

The preferred solution is a new stopbank, designed to protect against a 1-in-100-year flood. The design includes embankments and some road raising on the Omāhu side of Taihape Road to ensure protection doesn’t shift the risk elsewhere.

Ōhiti Road was hit hard by Cyclone Gabrielle. While most homes in the area avoided formal Section 72 notices, they were flagged as high risk for future flooding. A stopbank is the best option to provide targeted, reliable protection. It will give Category 2C properties 1:100-year flood protection and, just as crucially, buy time for safe evacuation in larger events.

Construction is scheduled to start in November 2025, once final designs are confirmed and consents secured. Major works are likely to take six to eight months, wrapping up mid-2026. Some stream works and erosion protection are already complete.

Project progress

Project starts | Planning and community engagement

Oct 2023 – Sep 2025
Concept and preliminary design completed. Engagement with mana whenua partners, landowners and community. Cultural, environmental and technical assessments carried out.

Design and consent process

Feb 2024 – Nov 2025
Final design signed off; land access secured. Resource consents lodged and approved under Order in Council. A site blessing marks the shift from plans to action, as works get underway.

Proposed construction period

Dec 2025 – May 2026
Stopbanks built. Drainage upgraded. Culverts, floodgates and supporting infrastructure installed.

Forecast completion

Second quarter 2026
Final stabilisation, planting and environmental enhancements. Safety checks completed. Community walk-throughs and closing karakia bring the project to its conclusion.

Email newsletters

Sign up

Sign up to receive project updates via email using the form below.

Follow this link if the form fails to load. online form.

Disclaimers and Copyright
While every endeavour has been taken by the Hawke's Bay Regional Council to ensure that the information on this website is accurate and up to date, Hawke's Bay Regional Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hawke's Bay Regional Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hawke's Bay Regional Council - www.hbrc.govt.nz / +64 6 835 9200 / info@hbrc.govt.nz