Resource Consent Application for Ohiti Flood Mitigation Works

Hawke's Bay Regional Council and Hastings District Council have received applications for resource consents from Hawke's Bay Regional Council's Project Team, for the construction of the flood protection mitigation works at Ohiti in accordance with the Severe Weather Emergency Recovery (Hawke's Bay Flood Protection Works) Order 2024 (Order in Council (OiC)).

Applicant’s details

Applicant: Hawke’s Bay Regional Council

HBRC resource consent application number: APP-131372
HDC resource consent application number: RMA20250327

Find out more about the Ōhiti Road project

Details of resource consent proposed activities

  • To undertake flood protection works under the Severe Weather Emergency Recovery (Hawke’s Bay Flood Protection Works) Order 2024
  • To construct a new Ohiti Stopbank of approximately 1,720m in length and generally 2-3m in height
  • To construct a new diversion swale (Ohiti Road Swale) of approximately 320 m in length and 2 m in depth
  • To construct a mitigation measure in the form of a stopbank (Chesterhope Upper Stopbank) of approximately 390 m east and north of Ohiwia stream
  • Road raising Taihape and Ohiti Roads
  • Cut and fill measures
  • To undertake diversion of floodwater in the Ohiwia Stream and Ngaruroro River arising from the proposed stopbank
  • Installation of a culvert across the the Ohiwia Stream
  • Vegetation clearance and soil disturbance
  • Discharge of dust associated with construction works
  • Discharge of sediment laden water to land or water
  • Discharge of solid contaminants within 20 m of a surface waterbody
  • Diversion and discharge of stormwater into water, or into land where it may enter water
  • The take and use of surface or groundwater (relating to the ‘take’ of drainage water if required as part of construction)
  • Swale outlet in the bed of the Ohiwia Stream
  • Disturbance of soil under the NESCS (in the area outside the OiC)
  • Earthworks exceeding Hastings District Plan volume thresholds (in the area outside the OiC)

The activity is a Controlled Activity in the area covered by the OIC and a discretionary activity for the area outside the OIC (see figure 3 of Resource consent Application for flood mitigation works Ohiti/Omahu).

Property location

The area of works is located between the Ngaruroro River and Taihape Road including a portion of Ohiti Road as shown in Figure 1.

Ohiti proposed location of works

 Figure 1: Location of proposed works

Comments on application

The comments period for this application is now closed.

The summary of comments and response to those comments is included in each council’s s42A Report as provided below

HBRC s.42A Report

HDC s.42A Report

The decision for the application was made on 22 October 2025

Hearings Commissioner decision

Loading...

Disclaimers and Copyright
While every endeavour has been taken by the Hawke's Bay Regional Council to ensure that the information on this website is accurate and up to date, Hawke's Bay Regional Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hawke's Bay Regional Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hawke's Bay Regional Council - www.hbrc.govt.nz / +64 6 835 9200 / info@hbrc.govt.nz